The original schedule was extended due to the repairs made on the reactor side.
Olkiluoton The nuclear power plant’s second reactor is producing electricity again, the nuclear power company says Power of Industry. Olkiluoto 2 returned to electricity production on Thursday morning after eight.
The original schedule was extended by a total of just over two days due to the repairs made on the reactor side.
According to Teollisuuden Voima, the annual maintenance of the triple reactor will continue until next Tuesday due to technical problems. Originally, the maintenance was supposed to be completed on Friday of this week.
The maintenance shutdown of Olkiluoto 1 is scheduled to start on Sunday.
#Nuclear #Power #Maintenance #Olkiluoto #completed #delays #producing #electricity