i-DE, the distribution company of the Iberdrola group, has managed to restore the electricity supply to more than 140,000 customers in the province of Valencia, which represents more than 90% of those initially affected.
According to the company, continues to displace its workers locality after locality to recover the service according to the access conditions and the facilities that allow it.
It has 80 generating sets which is proceeding to connect in those areas where it is technically possible. The connection of more than 44 of these groups in the affected localities such as Alborache, Alfafar, Alginet, Benifaió, Bugarra, Buñol, Cheste, Chiva, Gestalgar, Quart de Poblet, Montroy, Pedralba, Picassent, Real, Ribarroja, Siete Aguas, Torrent and Utiel, among others, and work continues on the rest of localities that continue without service.
It should be noted that in addition to the installation of the groups, the recovery of the electricity supply is being achieved in many of the affected populations. through the existing network.
The company, in coordination with the Emergency Control Center of the Generalitat Valenciana, continues to schedule actions to recover the electricity supply in the facilities that They supply the water treatment plants of the affected municipalities.
Since the beginning of DANA (isolated depression at high levels) i-DE has mobilized an approximate total of 500 people both from the Valencian Community and from other regions in the rest of Spain to proceed with the repair of the affected facilities as soon as access is possible.