Today ends the term given by the Ministry for projects to comply with environmental legislation, otherwise they will lose the permit to evacuate energy to the electricity grid
A dozen photovoltaic power plant projects presented in the Region, with a total power of 390.23 megawatts, have an uncertain future, having arrived without their homework done on the last day of the deadline granted by the Ministry for Ecological Transition to that they have approved all environmental procedures. Yes