There will be changes in the planning of Espai Barça. Although in the month of June, the season ended, the club planned to incorporate the works to install the field cover to the works to install the field cover, the entity has decided to postpone this phase of the works for one year. That is, until the summer of 2026, the tasks to install the cover will not begin. This change of planning is due to the fact that, to place the cover, the structure of the third grass to place the 1,400 tons of cable of its structure must be more advanced. Between three and four months will be needed at full dedication, so the works would be interrupted to adapt the stadium.
To raise the cover, between three and four months are needed, so the works would be interrupted to adapt the stadium
Once the roof wiring installation is finished in the summer of 2026, the fifth phase will arrive, the placement of the membrane of the same, which will be extended during the 2026-2027 season so the inauguration of the new spotify Campy Nou will arrive when the next elections to the presidency of FC Barcelona have already been held. Club sources estimate that the inauguration will be in October 2026. Four months later what was planned.
The operators also install the seats of the first and second grade
The same sources point out that the delay in the development of the works is because several imponderables caused by factors such as the availability of materials, the lack of labor or works not initially foreseen. These are aspects that have generated modifications in the execution calendars already very tight and optimistic from the beginning taking into account the size of the work.
Operators work to install the lawn during the next 10 weeks
Even so, the club insists that whatever this course is happening, they assure that in September, in the face of the 2025-2026 course the new stadium will be able to house 63,000 people. Of course, without cover that can cover the spectators and the Board of Directors itself on rainy days. There has also been a change in lighting that should be located on the deck. Due to the change of planning, a provisional structure will be created between the second and the third grade with the necessary foci to be able to see the parties well. There will also be a provisional access control system and restoration points.
Currently the 3,000 Limak operators have already cleared the entire future pitch. In ten weeks, that is, in mid -April, the Camp Nou will already have installed the grass and irrigation systems. As for the provisional accesses to return this course, the workers of Limak will also begin soon and, if everything goes well, to asphalt and level the future entries to the new Barcelona house to reopen this same course.
The club is still pending of some works licenses
From the club they are aware that many permits will need and that this same course go to obtain them. Beyond the rhythm of the works and other imponderables, Barcelona needs the sports permits of LaLig Fans go with a third grass under construction. The ideal plan of the club is that this first phase of works is ready in mid -April so that the cited agencies give them time to study the land before the aforementioned month ends. But in the club they also know that obtaining the consistory placets is neither easy nor fast. In addition, currently there is still the construction license for the lateral parking lot of an underground parking lot of 4,000 seats.
The entity has asked permission to the City Council to expand the work schedule 24 hours six days
As for the schedule of the works, to expedite the process, the Blaugrana entity works simultaneously to get a City Council permit in order to establish a third work shift with which you can work 24 hours six days a week. Currently, the usual schedule of the works with the use of exterior machinery is from 10 a.m. to 8 p.m. from Monday to Friday, with consent to continue between eight in the afternoon and 12 at night if they do not cause rumble or light pollution In the North Gol.
On the other hand, in the South goal the works must end at 10 pm. It also works on Saturdays from 10 a.m. to 8 p.m., but without using the open work plant in the Miniestadi area. Inside the field you can work until twelve at night as long as noise is made. It should be remembered that the residents of Les Corts have filed several complaints about the noise of the works. This afternoon a new meeting is scheduled between the members of Espai Barça leading Joan Sentelles and between 20 and 25 residents of the district.
At the same time and, after the cancellation of the European Rolling Stones tour, the club is still aware that the City Council and BSM confirm its application to be able to play in Montjuïc until this season ends in case the field is not ready in May. There are few voices of the club that consider that it will not turn until September next year.