There is just over a month left until summer begins in the Mexican national territory, and, despite this, high temperatures have already been recorded in almost the entire Mexican Republic. Under this understanding, it is worth knowing that there is a procedure that must be carried out if you want to save on the electricity bill issued by the Federal Electricity Commission (CFE)and we will give you more details shortly.
In this sense, if you want to save this coming summer on the electricity bill from the Federal Electricity Commission (CFE), the ideal is to proceed with the installation of solar panelsfor which a formal request must be made to the Mexican State electricity company.
{{title}}
{{/main}}
In this sense, if you want to install solar panels, you must sign an interconnection contract with the Federal Electricity Commission (CFE).
In this way, first of all, it should be noted that there are three types of interconnection contract with the Mexican State electricity company, and they are the following:
*Net Energy Metering (Net Metering): The CFE client consumes and generates energy in the same supply contract. This energy is subtracted from consumption.
*Net Billing: The electricity consumed that the State electricity company gives to the client is independent of the energy that the client generates and sells to the Federal Electricity Commission; That is, it does not subtract from your consumption.
*Total Energy Sale: The client sells all the energy it generates to CFE. Here there is no supply contract between the client and the State company.
For its part, after the user has selected one of the contracts for the interconnection of solar panels, he will have to submit an application to the electricity company, which can be found on the official website of the Federal Electricity Commission, in a center corporate customer service.
In turn, at the customer service center of the Federal Electricity Commission (CFE), the following requirements will have to be presented:
*Sketch of geographical location of your home.
*Single-line diagram of the power plant to be installed.
*Technical sheet of the generation technology used.
*Certificate of the power inverter (if applicable).
*Copy of the last receipt if you are already a client of CFE Basic Services Supplier.
Finally, we must not lose sight of the fact that although the process of interconnecting solar panels is free, it is required to carry out an interconnection study or works on the CFE electrical network, a price that is borne by the interested person. By concluding the process, you can go for your new interconnection contract.